The plant is now on site. Construction of the steel frame starting tomorrow......
CPE are a specialist producer of stainless steel pressure vessels. During 2012, CPE are adding a brand new stainless steel fabrication shop to their two existing workshops. The new workshop will be aimed at the offshore and nuclear industries, with state of the art design, equipment and work systems.
Tuesday, 31 July 2012
Friday, 20 July 2012
New cranes looking good!
Check out these beasts!
You only really get an idea of scale when you look at the chair in the 3rd picture.
We just need the building to put them in now.
When will it stop raining???
More delays - due to weather
Some of the stantions are so tall that they need to be painted outside and it just hasn't been the right weather for it.
Was 16th August- then 23rd - now apparently steelwork definitely will be on site 30th.
We need this building completing pretty quick - but apparently the shell should be complete in August still.
Some of the stantions are so tall that they need to be painted outside and it just hasn't been the right weather for it.
Was 16th August- then 23rd - now apparently steelwork definitely will be on site 30th.
We need this building completing pretty quick - but apparently the shell should be complete in August still.